3/16/07
DWP Power Upgrade Project - Email from the Construction Manager

To the Oaks Homeowners Association;

On behalf of
Mr. Mark Hollister,
Manager of Distribution Construction & Maintenance Section,
City of Los Angeles, Department of Water and Power.

This is a summary of the March 12, 2007 annual homeowners meeting held at the Immaculate Heart High School.

First let me say it was my pleasure to attend and give each of you an update on the projects that are currently on going and the others planned for the future. Know that Mr. Hollister and I, along with our construction crews are committed to provide you with the best customer service we can. Yes, in the past LADWP has fallen short of that commitment and for this please accept my apologies for any inconvenience this may have caused you.

Now let me summarize the meeting for you;

1. As you are aware LADWP is short staffed and dealing with the issues of the “brain drain”, Baby Boomers and their experience are retiring and walking out the door at an alarming rate. Lineman and Cable Splicers take 4 years to train to become competent workers.

2. LADWP has just finished negotiating with Labor Unions and Contractors to continue with our pole and cable replacement programs for three years; this will put more resources into the field repairing the wires and cables.

3. Along with the new contracts LADWP is in the process of updating our training programs in an effort to accelerate the training and increase the number of qualified workers, our program is now split to train Lineman and Cable Splicers in three years.

4. At this time there are several groups that are working on the Oaks area projects. Engineering and Design group, Overhead Distribution Design aka, “Spotting”, District overhead and underground crews and our Contract Operations group (CO).

5. In November you received a letter from our General Manager outlining the scope of the projects and the estimated start date of April 2007 and an approximate duration of 2 years to complete the upgrades. LADWP started the work on Phase 1, November 2006, so that puts us ahead, not by much, but we’re ahead.

6. The schedule of the projects are as follows;

Phase 1 – UG cable upgrade in the area of Los Feliz, Western, Live Oak and Hobart is estimated to be completed by May 1st.

Phase 2 - OH conductor upgrade on Canyon Ave is also estimated to be completed by May 1st

Phase 3 - UG cable upgrade in the area of Live Oak West, Verde Oak and Mountain Oak will be worked by our CO group, this project is estimated to begin in July 2007 and will take at least 6 to 7 months to complete, this is due to the amount of circuit switching and “jumpering or by-passing” of the cables.

Phase 4 - OH conductor upgrade also on Canyon Ave. is in the design stage and expected to be completed by April 1st, this job is more then 1000 hours of work and is estimated at 8 to 10 weeks to complete. Our Lincoln Heights District crews are scheduled to start this job as early as June 1st, although it maybe as late as July 1st with an estimated completion of October 2007.

Phase 5 – the final UG cable upgrade in the area of Live Oak West, Holly Oak, Hill Oak, Wild Oak, Red Oak and Park Oak is estimated to start January 2008, at this time it is estimated to be 6 to 8 months of work.

LADWP is committed to provide the best service possible and part of that commitment is communications, with that in mind LADWP has assigned a single point of contact during construction stages. This liaison is Mr. Jay Puklavetz, Central District Superintendent, who will dispatch e-mails to your contact Mr. Rainer Standke who will forward the information to all of the owners.

As always please feel free to contact either Mr. Puklavetz or myself with your concerns, comments and/or complaints and we will try to response in a timely manner.

Mr. Jay Puklavetz, Central District
(213) 367-6420
jay.pulavetz@ladwp.com

Thank you for your time and patience.

Andy Sparks, Distribution Construction & Maintenance Group
(213) 367-1883
andy.sparks@ladwp.com

Home Boardmembers About The Oaks Membership Newsletter Meeting Minutes News Archive Oaks Announcements Interim Control Ordinance WebLinks Useful Phone Numbers